Nevitt Elementary School
Welcome to the construction website for Nevitt Elementary School

Project Description:

This project includes a complete campus rebuild of the existing Nevitt Elementary School. There will be multiple phases of construction in order to keep the campus fully operational during construction. The new school will be 95,000 square feet and will feature a two-story classroom building, separate administration building, and new cafenasium building. Additional new site amenities include new play fields, new play structures, new parking, and 21st century school amenities including an outdoor classroom space designed in collaboration with the school PBL/PACE students.

Construction Duration: February 2018 – July 2019

Project Contacts:

Project News
Last PACE Class Before Summer Break
Last week we had our final PACE class before summer break. We reviewed the final design and overall budget for the student’s new Outdoor Classroom. We also explained next steps and when they can expect their vision to become a reality within th
Read More
PACE Students Designing Outdoor Classroom Space!
PACE Students are designing an outdoor classroom space for the new campus The students are being guided by HDA Architects and Concord General Contracting They have been given a budget & list of potential materials that can be used
Read More
Groundbreaking Ceremony
We had a fun Groundbreaking celebration on Friday, March 9, 2018
Read More
Project Updates
Ribbon Cutting Ceremony
It’s a wrap! After spending a year and a half under construction we are happy to hand the new campus over to the students and staff at Nevitt to enjoy for years to come. Miss the ceremony? Check out the Ribbon Cutting video and photos from the cele
Read More
5/22/19 Updates
Building B: Exterior/interior wall framing Rough MP&E/fire ongoing Roof are being dried in Exterior painting ongoing Interior floor grinding finished Exterior concrete being prepped/poured Site: Dirt grading ongoing Landscaping ongoing  
Read More
5/8/19 Updates
Building B: Interior framing Interior rough plumbing Interior rough electrical Interior rough HVAC Decking finishing today Floor grinding has started Interior/exterior block filling going on Masonry finished Steel canopies started Site: Dirt work 2 o
Read More
3/13/19 Updates
Building B: Block is being laid at gym/classroom areas Underground plumbing is 99% done Underground electrical is 90% done Site: Underground utilities are being installed Phase 1 punch items are being completed.
Read More
2/27/19 Updates
Building B  Footing are poured Block stems have started Electricians are installing conduits in block Site Work: Site dirt grading going on
Read More
2/13/19 Updates
Earthwork ongoing. Engineered soils and pad complete where ‘B’ building is to be constructed. Excavations for building footings is complete. Rebar installation for new footings is complete. Concrete footings poured and complete.  
Read More
1/30/19 Updates
Building B : Demo is complete Pad dirt work has started Site demo is ongoing Building C/A : Night work continuing for punch work
Read More
Phase 1 Complete – Entering Phase 2
Progress: Phase 1 Admin and classroom buildings are being used by staff and students. Playground and play equipment outside of the classroom building being used. Final touches and construction corrections are ongoing. Crews are currently working even
Read More
12/12/18 Updates
Final interior flooring being installed. Final building keying underway. C building final cleaning has started. Interior room signage scheduled for this week. HVAC testing and balancing. Supergraphics (interior graphics) started in both buildings. Se
Read More
11/30/18 Updates
Building C: Painting stairwells Installing flooring/final grinding Finishing millwork Finishing glazing Finishing HVAC/start up Finishing ceilings Finishing trim throughout Building A: Painting Trim through out Final grinding finished Ceramic tile fi
Read More