• Final interior flooring being installed.
  • Final building keying underway.
  • C building final cleaning has started.
  • Interior room signage scheduled for this week.
  • HVAC testing and balancing.
  • Supergraphics (interior graphics) started in both buildings.
  • Setting of toilet fixtures nearly complete.
  • Install of glass nearly complete.
  • Toilet partitions and toilet accessories starting later this week.
  • Site fencing installation underway.
  • Installation of artificial turf in courtyard of C is underway.
  • Site concrete sidewalks and curbing nearly complete.
  • Landscape irrigation installation nearly complete.
  • Trees to be on site today for installation.Footings for new fabric shade structures installed.