Building B:

  • Interior framing
  • Interior rough plumbing
  • Interior rough electrical
  • Interior rough HVAC
  • Decking finishing today
  • Floor grinding has started
  • Interior/exterior block filling going on
  • Masonry finished
  • Steel canopies started

Site:

  • Dirt work
  • 2 of 3 basketball courts concrete poured
  • Basketball back stops finish this week
  • Playground/swings finished
  • Canopies installation finished
  • Site chain link fencing 70% done