Brooke Banowetz
Ribbon Cutting Ceremony

It’s a wrap! After spending a year and a half under construction we are happy to hand the new campus over to the students and staff at Nevitt to enjoy for years to come. Miss the ceremony? Check out the Ribbon Cutting video and photos from the celebration below.      

Read More
5/22/19 Updates

Building B: Exterior/interior wall framing Rough MP&E/fire ongoing Roof are being dried in Exterior painting ongoing Interior floor grinding finished Exterior concrete being prepped/poured Site: Dirt grading ongoing Landscaping ongoing  

Read More
5/8/19 Updates

Building B: Interior framing Interior rough plumbing Interior rough electrical Interior rough HVAC Decking finishing today Floor grinding has started Interior/exterior block filling going on Masonry finished Steel canopies started Site: Dirt work 2 of 3 basketball courts concrete poured Basketball back stops finish this week Playground/swings finished Canopies installation finished Site chain link fencing […]

Read More
3/13/19 Updates

Building B: Block is being laid at gym/classroom areas Underground plumbing is 99% done Underground electrical is 90% done Site: Underground utilities are being installed Phase 1 punch items are being completed.

Read More
2/27/19 Updates

Building B  Footing are poured Block stems have started Electricians are installing conduits in block Site Work: Site dirt grading going on

Read More
2/13/19 Updates

Earthwork ongoing. Engineered soils and pad complete where ‘B’ building is to be constructed. Excavations for building footings is complete. Rebar installation for new footings is complete. Concrete footings poured and complete.  

Read More
1/30/19 Updates

Building B : Demo is complete Pad dirt work has started Site demo is ongoing Building C/A : Night work continuing for punch work

Read More
Phase 1 Complete – Entering Phase 2

Progress: Phase 1 Admin and classroom buildings are being used by staff and students. Playground and play equipment outside of the classroom building being used. Final touches and construction corrections are ongoing. Crews are currently working evenings to make corrections. Phase 1 parking lot is complete and is being used. Minor adjustments in signage and […]

Read More
12/12/18 Updates

Final interior flooring being installed. Final building keying underway. C building final cleaning has started. Interior room signage scheduled for this week. HVAC testing and balancing. Supergraphics (interior graphics) started in both buildings. Setting of toilet fixtures nearly complete. Install of glass nearly complete. Toilet partitions and toilet accessories starting later this week. Site fencing […]

Read More
11/30/18 Updates

Building C: Painting stairwells Installing flooring/final grinding Finishing millwork Finishing glazing Finishing HVAC/start up Finishing ceilings Finishing trim throughout Building A: Painting Trim through out Final grinding finished Ceramic tile finished Installing glazing Grid finished Site: Paving finished Forming benches/sidewalks/pouring Started fencing Final adjustments of underground utilities Final grading Installing landscaping

Read More