Progress:

Phase 1

  • Admin and classroom buildings are being used by staff and students.
  • Playground and play equipment outside of the classroom building being used.
  • Final touches and construction corrections are ongoing. Crews are currently working evenings to make corrections.
  • Phase 1 parking lot is complete and is being used. Minor adjustments in signage and striping are in the works.

Phase 2

  • Temporary fencing adjustments on site are nearly complete.
  • Demolition of the existing boat building and the existing main building is nearly complete.
  • Once this demo is complete, earthwork and site cleanup will start for the new cafenasium.
  • Abatement of the (2) existing modular buildings on the east side of campus is complete.
  • Demolition of the modular is scheduled, followed by demolition of the existing parking lot.